Prep and Pelican building progress
Prep
At the Prep, concreting works have been completed. The first floor and roof steelwork is in place and the internal blockwork commenced in the New Year.
Pelican
The Pelican Hall now has its roof and plastering is being undertaken inside.
Classroom 1CB has been completed early and was occupied by the pupils immediately after the New Year. During the Christmas holiday advantage was taken of the pupils’ absence to carry out certain alterations not possible in term time.